Exercise No. 22: Capacity Planning

Transfer the following verbal description into an EPC

a) On occurrence of a capacity shortage, the system verifies whether to perform an interactive or an automatic calibration. The system used is PP (production planning).

b) For interactive calibration the manufacturing department starts the calibration run leading to any of the following events: production is rescheduled or tools are relocated or additional resources are allocated or the working sequence is modified.

c) Thereafter the calibration is completed. If capacity shortage still persists and another run is indicated, interactive calibration will be executed again; otherwise, the calibration is aborted.

d) In any case, the manufacturing department examines the whole network for functional failures at the end of the process.