Exercise No. 13: Total Material Requirements Planning

Transfer the following verbal description into an EPC

a) When a MRP run is to be executed, the manufacturing department specifies the plant using the production planning system (PP).

b) Then the manufacturing department specifies the MRP parameters (planning type, category of purchase requisition, category of schedule line creation, MRP list creation category, planning mode, lead time scheduling to be executed or not).

c) After specifying the parameters, the MRP run can be launched. The result of the run leads to the creation of a combination of the following events, which may be subject to further processing:

d) "Purchase Requisition", "Scheduled Quantity", "Dependent Requirement", "Planned Order", "Capacity Load", "Planning Result", and .MRP List".